Solar, Wind, and GeoThermal Power - Hanger / Home
Approaching runway 01
View of Butler Airpark Looking East
---------->
Butler Airpark in the Fall of '07     4KS7     Frequency 122.87      2,687' x 40' Turf Runway       Latitude 37º33'32"  Longitude 97º03'53"
                                                                                   Approaching Runway 01
        Break Ground 9/22/07
Culvert is Installed, and the Driveway is Marked Out
<-------
Tawakoni Road
Approaching Runway 19
At Butler Airpark
LOW & SLOW !!
Fly By My Lot
Current Airplane Factory
6 Acre Lot Plot
Tawakoni Road
9/22/07  Trees removed, and 24" X 30' Culvert Installed
Lots of Rain This Spring
Beginning of April '08     4 Tandem Loads of 6" Limestone
4 Tandem Loads of 2" Limestone
The Driveway is 600 Feet Long
Coming Back Down the Driveway
Heavy Spring Rains have Already Washed
out a lot of the Topsoil & New Grass
Lots More Rain...Lots More Mud !!   They call it 'Gumbo Clay'.  It's Hard as a Rock when it's dry, and Sticks to Everything when it's Wet.
Building Permit Issued on 3/12/08
Well Drilled & Pump - Installed
              End of April '08
This Is What It's All About !!
More Rain...Lots More Mud
High Voltage Underground Electric Cable & Transformer,  Installed Beginning of May '08
Temporary Electric Pole
Within Days, Heavy Rain for 3 Days Straight, Washed every bit of dirt out of the ditch, and deposited it at the bottom of the Hill.
Scratching Out the Gumbo Clay...Didn't hit a single rock
Running Water !!!
The First Ditches that were Dug, were for the Water Lines to the Building
Plenty Deep to Avoid Freezing
So Much Rain this Spring & Summer...Every Single Ditch that I Dug out there, Filled up with Rain Water, Before I was Able to Install the
Utility, and Fill the Trench Back In
Catherine's Piper Cherokee
Short Final at Newton Airport, where she Keeps her Plane.
Here are some Pictures I took from Her Plane.  She flies Much Higher than the Ol' Pietenpol !!
This Tarp Proved to be Inadequate to keep
Rain Water Out of the Hole the Tank is in.
Catherine  Said Spending some Leisure Time out at the Property was very Therapeutic
1000 Gallon Concrete Tank, to Store the Solar Heated Water, is In the Ground,
Below the Concrete Floor
Dig More Trenches, and they Filled up with
Rain Water, before they were Complete
Some of the Drain Pipes that are Needed
The Tank was Well Insulated All the Way
Around, with Several Layers of 2" Styrofoam
All this Rain Sure Makes the Grass Green !!
A Very Well Manicured Grass Runway
The Case Trenching Machine Finally Broke the Old Wore Out Chain
I managed to Wrestle the New Chain / Teeth
on the Machine, and it is Now at Least 3
Times as Fast, Digging a Trench
Been Working the Ol' Truck Really Hard
The 3/4" Lines that go to the GeoThermal Cooling were Insulated, and Installed in
Conduit, Under the Concrete Floor
Some of the Water Lines, and Drain
Pipes are In the Ground
Before I got the Tank Full of Well Water - More Rain, and It Managed to Float the 8000 Pound Concrete Tank, Up Out of the Ground !!
                                                                                                   I couldn't Believe It !!
The Trencher Makes Quick Work of Digging a Long Drain Pipe Trench
I had to get the Truck Back Out There, to Lift the Tank Back
Out of the Ground, Dig the Mud Out of the Hole, Set the Tank
Back Down, and Re-Insulate all around the Tank
I also used the Excavating Machine
to do a Lot of the Final Grade Work
Here are the Lines that Go to the Solar
Collectors
The 1" Lines that Go To the Solar Collectors, are Insulated, and Encased in Conduit.
 This Will Be a 'Drain Back System', so the Lines are Sloped Back to the Tank.
Cold Water Lines are Blue 3/4" Pex Plastic, and the Hot Water Lines are Red 3/4" Pex Plastic, and are Insulated for Their Entire Length
The Tank was Lifted Out with the Truck, while I dug out the Hole with the Excavator, then Set Back Down in the Hole, and Re-Installed all
the Styrofoam, and now with the well working, I filled the tank with water.
These Little Excavators are fairly easy to run, and are Unique
in their Ability...they should be, at $240 a Day  to rent.
These are the first pictures I took of the lot, after I purchased it
I built a roof over the tank, but rain water still got in.  I'm having some bad luck with this installation.  The tank stayed in the ground this
time, but the insulation floated up, lifting the roof with it.
The Plan:
A Two Bedroom Home, enclosed in a Steel Building that serves as a Hanger, and a Shop, and
Depends on Solar Energy, Wind Energy, and GeoThermal Cooling to Support all the Energy
Requirements.
Low Fly Over, during the Winter of 2008
Spring 2009 has Sprung !!   These shots are taken on May 4
                                                                    CONCEPT
Design and Build a Hanger / Home that produces ALL the energy it needs to Heat & Cool the
interior, heat the domestic hot water, provide interior and exterior lighting, power a 100%
Electric Car, Truck, and Electric Lawn Tractor :
Ultimately, to Disconnect from the Utility Grid, and / or Sell Excess Energy back to the Grid.
All Construction Material, and Interior Furnishings, are Non - Flammable : No Need for Fire
Insurance.
Note :
Solar, Wind, Geo Thermal,  and Gravity are not only Renewable Energy Sources to be used
for ALL the Energy Requirements, but So far, the Politicians haven't figured out a way to Tax
Them !!

                                                                
 SOLAR  HEAT
This system utilizes over 600 sq. ft. Of Hot Water Solar Collectors.    It is a 'Drain Back
System', where as when the collectors heat up to a temperature that is higher than the water
in the tank,the pump kicks on, and circulates the water through the collectors, and back to
the tank.   When the temperature drops lower than the water in the tank, the submersible
pump turns off, and the water in the Solar Collectors drains back into the tank - to prevent
freezing. Photo voltaic (PV) Cells charge a Central Bank of Batteries, to provide most of the
Electric Energy.

                                                               
 WIND  ENERGY
Help Charge the Central Bank of Batteries, to produce the current to power the pumps for
the heating system, as well as any other electrical needs of the dwelling.

                                                            
 CONCRETE  HEAT
Pump the Heated Water from the tank, and circulate it through the pex tubing that is in the
concrete floor, and distribute the heat to the selected zones.

                                               
 PELLET  STOVE  BACK UP  HEAT
In the event of a period of cloudy days, the Pellet Stove will automatically light the flame, and
a pump will circulate the water through the firebox, to the Hot Water concrete holding tank.

                                                         
 GEO  THERMAL
There are Two 3/4  Pex Plastic Lines that are buried in a trench that is 6 feet deep, and 400'
long.  This water will circulate through the concrete to cool the dwelling during the summer
months.
It Also can Provide the Heat Transfer Medium to Run a Heat Pump.
Little House on the Prairie
A lot of  places the grass seed washed away, and it is coming up in small patches
Kansas is known as the 'Sunflower State', therefore...Grow Sunflowers !
In  Early March, I planted over 600 lbs of  Kentucky 31  Tall Fescue Grass Seed, and spread over 500 lbs of Starter Fertilizer.  
A  LOT of the grass seed washed away during a Gully Washer Rainfall, and ALL of the Hay Cover  Blew Away.
Hot Water Distribution Header Location
The 400' Long and 6' Deep Geo Thermal Trenches are settling, and opening up.
Some Places need Re-Seeding
These  Two outside faucets are Located on the North End, and South End of the Building.
One of the 16 Sprinkler Heads
I set up a Timer, to run the Deep Well Pump for 1 hour
in the Late Evening Hours.  The 1hp pump can't put
out enough water for all the Sprinklers, so I have to
Valve it for Half at a Time.
This is the Header, where the 1" Deep Well Line enters the building at
the Northwest corner, and distributes to the Domestic Water, North
Outside Faucet / Irrigation Faucet, and South Outside Faucet.
Irrigation Faucet out in the Yard.
One of the Last Trenches, is for the Domestic
Sewage Drain Lines, that goes to the Lagoon.
Here is a Submersible Float Pump, to keep most of the
water out of the Trench.
The Driveway is 600 Feet Long.
Almost the entire 6 Acres are in View.
Scratching Up the Earth
This shot was taken during 2nd Week of May
Here is one of the Storms that Washed Away
the Grass Seed !!
Old Faithful
Sprinklers In Action
April 24 Milestone - The Drains Are Complete, and All Glued Together !!
Took Vacation the last 2 weeks of June, to Dig the Footings, and Pour the Concrete
Montanez Construction Crew did the Concrete Work  
The Concrete came from Haysville
North West Corner - Looking South East
Blocked Off for Footing of the Solar Collectors
The Column Locations are 2 Feet by 2 Feet.
Foam Insulation - One Inch x Two Feet Deep - is to Help Reduce Heat Loss from the Concrete Slab Floor Heating System.
The Concrete was Done in Two Separate Pours.  For the Second Pour, These 2 x 12's were Formed on Top of the First Pour.
North East Corner - Looking West
These Shots are Along the East Wall of the Building.
North West Corner - Looking East
North East Corner - Looking South
South East Corner - Looking North West
North East Corner - Looking South West
This is the 72' long South Wall - Along
Which there will be Solar Collectors
along its Entire Length.
On Approach - Looking East
The Building is 72' x 80'
Wildflowers I'm Going to Transplant
              July 6 of 2009
Overall View - Looking South East
Shop Door on West Wall
North West Corner
East Wall where Kitchen Will Be
East Wall where Hanger Door Will Be
The Actual Building Dimensions are at
the Inside of the Notch in the Concrete
The Notches in the Concrete is where
the Siding will Overlap
Screenings from the Local Quarry is
used for a base under the Insulated
Concrete Slab Floor
These are the Two 1" Water Lines for the
Solar Collectors, and Electrical Conduit
Lots More Yard Work To Do, but there Is
some Grass Growing.
The Footer / Stem Wall is Insulated Inside
and Out, Below Grade, as well as Above
Grade.  This is the Hanger Door Opening.
Backfill Dirt Up Against the Stem Wall